Project Name

Four laning of Nanasa to Pidgaon from (Design Ch.95+000/Existing Ch.95+000) to (Design Ch.142+445/Existing Ch.141+530) Section of NH-47(Old NH-59A) (Design Length -47.445km) under Bharatmala Pariyojna Phase-I (Economic-Corridor) in the State Madhya-Pradesh on HAM Mode-Package-III (Indore-Harda).

Scope of Work

Rehabilitation, up gradation and widening of the existing carriageway from 2 lane (7m Carriageway) to 4 Lane standards with construction of new pavement. Construction and/ or rehabilitation of major and minor bridges, culverts, road intersections, interchanges, drains, etc. Operation and maintenance of the Project.

Client

National Highways Authority of India (NHAI)

Construction Period

2 years (730 days)

Length in KM

47.445 kms

O&M Period

15 years

Concession Agreement Date

13.7.2020

Pavement Classification

Flexible Pavement for Main Carriageway and Service/Slip Road Rigid Pavement for Toll Plaza

Appointed Date